Question #: 392
Topic #: 1
[All PK0-004 Questions]

In a projectized organization, a project manager has a need for a testing resource. The first place the project manager should look for this resource is:

  • A. a dedicated resource pool
  • B. an allocated resource pool
  • C. a shared resource pool
  • D. a benched resource pool
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Manson_Ng
Highly Voted 4 years, 3 months ago
It should be A
upvoted 10 times
elvancedonzy
3 years, 11 months ago
Dedicated resources are the ideal scenario for a project manager because you have full authority and control of the resource time and the tasks they work on. You don't have to coordinate schedules with another manager or fear having the resource pulled off the project because of an "emergency" in the functional area.
upvoted 1 times
...
...
joe99999
Most Recent 2 years, 1 month ago
B is correct. The resources are already allocated. projectized - an organizational structure in which the project manager has full authority to assign priorities, apply resources, and direct the work of persons assigned to the project
upvoted 1 times
...
ItsMeAgain99
2 years, 6 months ago
D. Benched resources - they're free and ready to be assigned for use. Any of the other choices are in use and would have to be re-allocated carefully.
upvoted 1 times
...
Manzer
2 years, 7 months ago
Selected Answer: D
Bench resources. They are waiting for a project. Dedicated are working on a project now.
upvoted 1 times
...
xparta300
3 years, 7 months ago
Shared resourcesResources that are used for multiple projects and must be managed assuch. Dedicated resources Resources that have been committed for your project's use. Benched resources Skilled resources that are retained during downtime but are notperforming "billable" tasks. The benefit is that they can be put intoservice immediately when the need arises. Low-quality resources Resources that do not possess specialized skills or qualities.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago