In a projectized organization, a project manager has a need for a testing resource. The first place the project manager should look for this resource is:
Dedicated resources are the ideal scenario for a project manager because you have full authority and control of the resource time and the tasks they work on. You don't have to coordinate schedules with another manager or fear having the resource pulled off the project because of an "emergency" in the functional area.
B is correct. The resources are already allocated.
projectized - an organizational structure in which the project manager has full authority to assign priorities, apply resources, and direct the work of persons assigned to the project
Shared resourcesResources that are used for multiple projects and must be managed assuch.
Dedicated resources Resources that have been committed for your project's use.
Benched resources Skilled resources that are retained during downtime but are notperforming "billable" tasks. The benefit is that they can be put intoservice immediately when the need arises.
Low-quality resources Resources that do not possess specialized skills or qualities.
upvoted 1 times
...
This section is not available anymore. Please use the main Exam Page.PK0-004 Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Manson_Ng
Highly Voted 4 years, 3 months agoelvancedonzy
3 years, 11 months agojoe99999
Most Recent 2 years, 1 month agoItsMeAgain99
2 years, 6 months agoManzer
2 years, 7 months agoxparta300
3 years, 7 months ago