Tasks A and B have a duration of two days. Task A starts on Day 1, and Task B starts on Day 3. Tasks C and D have a duration of three days, and Task E has a duration of four days. Task C starts after Task A. Task D and E start after Task C. If Task A starts on December 15, which of the following is the anticipated start date for Task D?

  • A. December 18
  • B. December 19
  • C. December 20
  • D. December 21
  • E. December 22
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
abhnn
Highly Voted 4 years, 5 months ago
This should be C
upvoted 12 times
...
sarndr04
Highly Voted 4 years, 2 months ago
Task A 15th to 16th + Task C 17-19 Dec - So task D starts on Day 20
upvoted 10 times
...
joe99999
Most Recent 2 years, 1 month ago
20 is the only answer. A=2 C=3 15+2+3 = 20
upvoted 1 times
...
Geodude
2 years, 4 months ago
Selected Answer: C
Like sarndr04 said its C - Day 20
upvoted 1 times
...
ExamTopics274
2 years, 5 months ago
Selected Answer: C
Answer is
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel