Exam PK0-004 topic 1 question 321 discussion

Actual exam question from CompTIA's PK0-004
Question #: 321
Topic #: 1
[All PK0-004 Questions]

During an ad-hoc meeting, the PM notifies the sponsor that while the project is on schedule, material costs have increased and the project is over budget. To save the project, the PM request a material contract with a less expensive vendor. The sponsor approves the change, and project comes in within target tolerances.
The company, however, receives numerous stakeholder complaints.
Which of the following is the MOST likely cause of these complaints?

  • A. The quality of the deliverable decreased due to the rising material cost.
  • B. The PM did not follow the project communication plan.
  • C. Quality assurance actions were not adjusted for the vendor change.
  • D. The change was not documented and approved.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
TreeeSon
2 years, 1 month ago
Given answer looks fine. It is stated that the PM lets the stakeholder know about the change and the sponsor agreed. That rules out B and D. C wouldn't make sense cause the project sponsor would've been involved in the project processes. My thinking is project over budget due to vendor>new vendor found> sponsor notified and approved change > budget back in target parameters > deliverables arrive and sponsors not happy. This leads me to believe the new vendor provided low quality material.
upvoted 1 times
...
Domdom120
2 years, 9 months ago
This has to be B - Did not follow the communication plan - leading to upset stakeholders. It says the change was approved and it seems the only people upset with it are those that were not informed of the change.
upvoted 2 times
...
[Removed]
2 years, 10 months ago
Selected Answer: D
This one is confusing. I see the answer could be quality because of less expensive materials however, it doesn't state they are using a lower grade, just a different vendor. So, this is unknown. Most of all, I see D. The change was not documented and approved This seems more plausible since the question states the PM got approval from the project sponsor and not the CCB. The sponsor might approve of the change but the change still needs to go through the change management process and the CCB needs to approve the change and the change needs to be documented and communicated.
upvoted 1 times
...
devildog
3 years ago
It says the project came within the target tolerances, meaning quality did not suffer. I honestly think the answer is that the PM did NOT adhere to the Communications plan, letting key stakeholders know of the change, this would explain their frustration. It says the change was approved by the project sponsor.
upvoted 3 times
...
sTryogetOn
3 years, 3 months ago
Selected Answer: D
Agree with abhnn, it should be D.
upvoted 1 times
Rob0645
3 years, 1 month ago
it literally says in the question (The sponsor approves the change )
upvoted 3 times
...
...
abhnn
4 years, 5 months ago
This should be D
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago