During a brainstorming session, a team member expressed concerns that solar flares could cause intermittent outages for those individuals working on the project. Which of the following would be the best tool to communicate this information to stakeholders?

  • A. Status report
  • B. Issue log
  • C. Risk report
  • D. Risk register
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
stinkle
2 weeks ago
Selected Answer: C
isk Register is the document used to track and manage risks, the Risk Report is typically used to communicate the status of risks to stakeholders. If the project manager needs to inform stakeholders about a potential risk (like the concern about solar flares causing outages), a Risk Report would be the best tool for communicating that information, as it provides a summary of the risk’s impact, likelihood, and any mitigation or contingency plans.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago