exam questions

Exam PK0-004 All Questions

View all questions & answers for the PK0-004 exam

Exam PK0-004 topic 1 question 2 discussion

Actual exam question from CompTIA's PK0-004
Question #: 2
Topic #: 1
[All PK0-004 Questions]

Which of the following are characteristics of a project? (Choose two.)

  • A. Ongoing
  • B. Temporary
  • C. Start and finish
  • D. Achieving a goal
  • E. Consisting of milestones
  • F. Restricting the budget
Show Suggested Answer Hide Answer
Suggested Answer: BC 🗳️
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 27

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
ramrod1738
2 years, 2 months ago
The characteristics of a project are: B. Temporary: Projects have a defined start and end date and are intended to be temporary in nature. Once the project is completed, the project team is typically dissolved. D. Achieving a goal: Projects are undertaken with the specific goal of producing a unique product, service, or result. The project is considered successful when the goal is achieved. Other options, such as ongoing (A), start and finish (C), consisting of milestones (E), and restricting the budget (F), are all aspects of project management that may be part of a project, but they do not define a project in and of themselves.
upvoted 2 times
...
cepojo
2 years, 2 months ago
Selected Answer: BC
Projects have a defined start/end, making them temporary by nature. CBT Nuggets
upvoted 2 times
...
boxv4
2 years, 8 months ago
I was watching a video in udemy about this. And the explanation I got was on point. A project is temporary, meaning it has a start and a finish. An operation is ongoing, it will run for an indefinite amount of time.
upvoted 4 times
...
Lee_Stahla
4 years, 4 months ago
I thought goal was an answer as well, but then I realized that running a marathon is achieving a goal but it is not a project. A project achieves a delivered product or services. Cue face palm. This test is very technically tricky.
upvoted 2 times
HelloMyNameIs
3 years, 11 months ago
I see where you're coming from, but to play devil's advocate, we can fit the other potential answers into that same example. For instance, running a marathon is temporary but it is not a project, also running a marathon has a start and finish but is not a project. Goals can be strategic goals or more tangible goals such as a product. I don't know what to think of this question, as I see it there are three answers. I just hope this question doesn't appear on my exam.
upvoted 1 times
...
...
LrnTday3131
4 years, 8 months ago
The achieving a goal is correct as well.. the question is out of the three which two do you chose. Unique: A project is typically undertaken to meet a specific business objective. It involves doing something new, which means that the end result should be a unique product or service. These products may be marketed to others, may be used internally, may provide support for ongoing operations, and so on. Temporary: Projects have definite start and end dates. The time it takes to complete the work of the project can vary in overall length from a few weeks to several years, but there is always a start date and an end date. Reason or Purpose: A project comes about to fulfill a purpose. This might include introducing a new product, fulfilling a business objective or strategic goal, satisfying a social need, and any number of other reasons. It's important to document and communicate the purpose and reasons for the project so that team members remain focused on achieving the goals of the project. Stakeholder Satisfaction: A project starts once it's been identified, the objectives have been outlined in the project charter, and appropriate stakeholders have approved the project plan. A project ends when those goals have been met to the satisfaction of the stakeholders.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago