Exam PK0-004 topic 1 question 202 discussion

Actual exam question from CompTIA's PK0-004
Question #: 202
Topic #: 1
[All PK0-004 Questions]

A new stakeholder has requested the status and progress reports for the project milestones. Which of the following documents should the project manager address FIRST?

  • A. Project communication plan
  • B. Project status report
  • C. Project management plan
  • D. Project backlog
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
SQLDON
Highly Voted 3 years, 11 months ago
The answer should be B based on Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 328
upvoted 6 times
Treymb6
3 years, 1 month ago
Second this. Project Management Plan defines how the project will be carried out, it shouldn't have status updates on milestones.
upvoted 2 times
brown705
2 years, 9 months ago
Third this.
upvoted 1 times
...
...
...
HCEYLAN
Most Recent 2 years, 2 months ago
Yeah, I also chose B. The wording is bad with this question or the chosen answer is wrong.
upvoted 1 times
...
Noralie
2 years, 2 months ago
project+ textbook states: project management plan is thefinal, approved documented plan that you’ll use throughout the remainder of the project to measure project progress and, ultimately, project success. The key components of the project management plan include the following documents: Scope statement Project schedule Communication plan Resource plan Procurement plan Project budget Quality management plan Risk management plan it says more but i dont think i can get it all in here. but PmP may be the correct answer here
upvoted 1 times
...
ItsMeAgain99
2 years, 6 months ago
Poor wording on sentence structuring on this question and open to various interpretations. Best choice would be Status Report since it contains a more comprehensive set of information. Nowhere on any Management Plan would contain project milestones, only baselines and performance measurements as a reference point.
upvoted 1 times
...
Braniac
2 years, 7 months ago
C. "Which of the following documents should the project manager address FIRST?" Keyword "FIRST" The project management plan, contains the communication plan, which will explain how to properly communicate with new stakeholders. Once this has been determined the PM will most likely produce a dashboard for the stakeholder containing the milestones. So first, the project management plan needs to be accessed.
upvoted 1 times
...
kevzzz
2 years, 8 months ago
Selected Answer: B
status report
upvoted 1 times
...
Ayoyemi
4 years, 10 months ago
C. Project management plan
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago