exam questions

Exam PK0-004 All Questions

View all questions & answers for the PK0-004 exam

Exam PK0-004 topic 1 question 276 discussion

Actual exam question from CompTIA's PK0-004
Question #: 276
Topic #: 1
[All PK0-004 Questions]

Which of the following captures unforeseen activities throughout the project that need attention and resolution?

  • A. Gantt chart
  • B. Action items
  • C. Project schedule
  • D. Meeting minutes
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Tangy_Lem
Highly Voted 4 years, 4 months ago
Action Items - A list of project actions that should be resolved in order to fulfill deliverables
upvoted 17 times
...
MJVIS
Most Recent 2 years, 2 months ago
Selected Answer: B
Action items. These answers are freaking me out. I feel like I am unlearning what I learned from the CompTIA study guide.
upvoted 3 times
...
POWNED
2 years, 4 months ago
100% B, would bet my left testy on it!
upvoted 3 times
...
sarndr04
4 years, 11 months ago
a Gantt chart is a visual view of tasks scheduled over time
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago