exam questions

Exam PK0-004 All Questions

View all questions & answers for the PK0-004 exam

Exam PK0-004 topic 1 question 29 discussion

Actual exam question from CompTIA's PK0-004
Question #: 29
Topic #: 1
[All PK0-004 Questions]

A carpenter on a project team reports there is insufficient time to accomplish tasks on schedule.
Which of the following is the FIRST step the project manager should take?

  • A. Assess the risk register's new items.
  • B. Review the task start and finish dates.
  • C. Obtain additional resources.
  • D. Analyze the assigned hours.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
abhnn
Highly Voted 4 years, 6 months ago
I believe it’s B
upvoted 6 times
...
izz123
Highly Voted 3 years, 10 months ago
The risk register is a list of risks that you can record in a simple spreadsheet that includes an identification number, risk name, risk description, risk owner, and response plan (or where the response plan can be located). This should be the first step, and then proceed according to the plan specified in the risk register.
upvoted 6 times
...
joe99999
Most Recent 2 years, 1 month ago
FIRST was the key word for me.. "The Risk Register or Risk Log is essential to the management of risk. As risks are identified they should be logged on the register and actions should be taken to respond to the risk."
upvoted 1 times
...
TreeeSon
2 years, 1 month ago
From ChatGPT: The FIRST step the project manager should take when a carpenter on the project team reports insufficient time to accomplish tasks on schedule is to review the task start and finish dates. Reviewing the task start and finish dates will allow the project manager to see if the carpenter's concerns are valid and if there are any other critical path activities that could be delaying the project. The project manager can also evaluate if the current schedule is achievable or if it needs to be adjusted. Once the project manager has reviewed the task start and finish dates, they can then analyze the assigned hours, assess the risk register's new items, and explore the possibility of obtaining additional resources if necessary. However, the first step should be to review the task start and finish dates to gain a clear understanding of the situation and identify any potential issues with the project schedule. This will help the project manager determine the appropriate course of action and prevent further delays or complications.
upvoted 2 times
...
ramrod1738
2 years, 2 months ago
B. Review the task start and finish dates. The project manager should first understand the cause of the insufficient time and if the task schedule is realistic. By reviewing the task start and finish dates, the project manager can assess if there are any issues with the schedule and identify potential solutions to address the insufficient time.
upvoted 2 times
...
ItsMeAgain99
2 years, 6 months ago
Wording on this question is not clear. Not finishing a task on time can be considered a realized risk, but since the task is already on the schedule, shouldn't the PM review the planned start and end dates first and go from there? B is certainly a valid answer.
upvoted 1 times
...
Braniac
2 years, 7 months ago
Issues and risks are different and should be treated differently. This seems like something that would be placed in an issue log and require action items. Functional managers deal with resources. risk register is irrelevant. Reaching out to the scheduler would seem more efficient than analyzing assigned hours. But Project Managers do prepare Gannt Charts with the WBS. containing work package start and end dates. So, B. Reviewing the task start and finish dates seems like the best choice.
upvoted 1 times
...
ChrisJ789
2 years, 7 months ago
No reference from the Official Project+ Student Guide? I think the answer is BS
upvoted 1 times
...
brown705
2 years, 9 months ago
I thought it was B as well. I do not understand why the risk register should be reviewed FIRST. The question did not say anything about risks, especially about adding NEW items to the risk register. Why would we not review what the schedule is supposed to be FIRST?
upvoted 1 times
...
AlvMicro
4 years, 1 month ago
I think it is correct the given response (A), since it says FIRST thing to do. Then , at a latter time, PM will check up for more resources to be added.
upvoted 1 times
...
Raddy_PM
4 years, 1 month ago
wat is the correct answer ? A?
upvoted 1 times
...
screwyui
4 years, 3 months ago
Tough one, think it's D.
upvoted 1 times
...
Rz10
4 years, 11 months ago
Wouldn't it be C. Obtain additional resource ?
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago