exam questions

Exam PK0-004 All Questions

View all questions & answers for the PK0-004 exam

Exam PK0-004 topic 1 question 23 discussion

Actual exam question from CompTIA's PK0-004
Question #: 23
Topic #: 1
[All PK0-004 Questions]

The executive sponsor asks a project manager to summarize the following for a project:
1. Final capital expenditures.
2. Anticipated cost of new employee resources to support the solution.
3. Maintenance estimates.
Which of the following information should the project manager provide?

  • A. Cost baseline
  • B. Burn rate
  • C. Cost variance report
  • D. Total project cost
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
tinytorr
Highly Voted 4 years, 11 months ago
A. Cost baseline
upvoted 10 times
...
ramrod1738
Most Recent 2 years, 2 months ago
Selected Answer: D
D. Total project cost The executive sponsor is asking for a summary of the final capital expenditures, anticipated cost of new employee resources, and maintenance estimates for the project. These are all components of the total project cost, which is the sum of all the costs associated with completing the project.
upvoted 1 times
...
ramrod1738
2 years, 2 months ago
The project manager should provide the Total Project Cost which would include the information requested by the executive sponsor such as the Final capital expenditures, Anticipated cost of new employee resources to support the solution, and Maintenance estimates. The Total Project Cost is an estimate of all costs required to complete a project and is typically documented in the project budget.
upvoted 1 times
...
yoyo1207
2 years, 3 months ago
chat gpt says TPC would include the final capital expenditures, the anticipated cost of new employee resources to support the solution, and maintenance estimates. The cost baseline would only include the budgeted costs for the project, which would not include the anticipated cost of new employee resources or maintenance estimates.
upvoted 4 times
...
[Removed]
4 years, 7 months ago
Estimates become final once you determine the cost baseline. (CompTia Project+ Study Guide, 2nd ed.)
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago