CompTIA Project+ Cert Guide: Exam PK0-004 (Pearson IT Certification, 2017) Project team members contribute project expertise and deliverables according to the project schedule. They provide estimations of task duration, costs, and dependencies.
The project team members would be best suited to contribute cost and time estimates for the project activities during the development of a Work Breakdown Structure (WBS).
Project team members are the ones who will be directly responsible for performing the project activities and have the most intimate knowledge of the work that needs to be done. They can provide realistic and accurate estimates based on their experience and expertise.
The project sponsor (B) is responsible for providing overall support and funding for the project, but may not have the technical knowledge to provide cost and time estimates.
The project manager (C) is responsible for overall management of the project, but may not have the detailed technical knowledge to provide cost and time estimates.
The project scheduler (D) is responsible for creating and managing the project schedule, but will typically use the cost and time estimates provided by the project team members to develop the schedule.
A. Project Team Members
Per CBT Nuggets course several times, "The project team members are in the best location to provide input regarding project costs and time estimates since they will be doing the work."
I agree it is the project team members as the sponsor is only interested in high level information and don't really care about the day to day activities of the project.
Project team members are responsible for a number of activities on the project. One of their most important duties is contributing deliverables according to the schedule. A partial list of other duties may include the following:
-Time and duration estimates for the tasks they are working on
-Cost estimates for deliverables or other project work purchased from outside the organization
Project Team Members is the correct answer
This section is not available anymore. Please use the main Exam Page.PK0-004 Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Extrarice
Highly Voted 4 years, 12 months agoarcheanchaos
Highly Voted 4 years, 9 months agoramrod1738
Most Recent 2 years, 2 months agocepojo
2 years, 2 months agoKamakurako
2 years, 4 months agoMJVIS
2 years, 5 months agoall4one
2 years, 8 months agoalazzani
3 years, 3 months agoSabie
3 years, 7 months agoJakesn
3 years, 8 months agoTom_123
4 years ago[Removed]
4 years, 8 months agorgreen83
4 years, 10 months ago