A WBS is being developed for a project.
Which of the following would be BEST suited to contribute cost and time estimates for the project activities?

  • A. Project team members
  • B. Project sponsor
  • C. Project manager
  • D. Project scheduler
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Extrarice
Highly Voted 4 years, 12 months ago
Pretty sure the correct answer here is Project Team Members
upvoted 30 times
...
archeanchaos
Highly Voted 4 years, 9 months ago
CompTIA Project+ Cert Guide: Exam PK0-004 (Pearson IT Certification, 2017) Project team members contribute project expertise and deliverables according to the project schedule. They provide estimations of task duration, costs, and dependencies.
upvoted 12 times
...
ramrod1738
Most Recent 2 years, 2 months ago
The project team members would be best suited to contribute cost and time estimates for the project activities during the development of a Work Breakdown Structure (WBS). Project team members are the ones who will be directly responsible for performing the project activities and have the most intimate knowledge of the work that needs to be done. They can provide realistic and accurate estimates based on their experience and expertise. The project sponsor (B) is responsible for providing overall support and funding for the project, but may not have the technical knowledge to provide cost and time estimates. The project manager (C) is responsible for overall management of the project, but may not have the detailed technical knowledge to provide cost and time estimates. The project scheduler (D) is responsible for creating and managing the project schedule, but will typically use the cost and time estimates provided by the project team members to develop the schedule.
upvoted 1 times
...
cepojo
2 years, 2 months ago
Selected Answer: A
A. Project Team Members Per CBT Nuggets course several times, "The project team members are in the best location to provide input regarding project costs and time estimates since they will be doing the work."
upvoted 1 times
...
Kamakurako
2 years, 4 months ago
Selected Answer: A
A makes the best answer
upvoted 1 times
...
MJVIS
2 years, 5 months ago
Selected Answer: B
Project Team Members
upvoted 1 times
...
all4one
2 years, 8 months ago
Selected Answer: A
The correct answer is team members.
upvoted 3 times
...
alazzani
3 years, 3 months ago
The correct answer is Project Team Members
upvoted 2 times
...
Sabie
3 years, 7 months ago
I agree it is the project team members as the sponsor is only interested in high level information and don't really care about the day to day activities of the project.
upvoted 1 times
...
Jakesn
3 years, 8 months ago
Yes, i believe answer is A.Project Team Members
upvoted 1 times
...
Tom_123
4 years ago
Project team members are responsible for a number of activities on the project. One of their most important duties is contributing deliverables according to the schedule. A partial list of other duties may include the following: -Time and duration estimates for the tasks they are working on -Cost estimates for deliverables or other project work purchased from outside the organization Project Team Members is the correct answer
upvoted 3 times
...
[Removed]
4 years, 8 months ago
Answer is project team members
upvoted 8 times
...
rgreen83
4 years, 10 months ago
yep, team members is correct
upvoted 7 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.