Which of the following panels would be best to facilitate a central termination point for all network cables on the floor of a company building?

  • A. Patch
  • B. UPS
  • C. MDF
  • D. Rack
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
2a45295
4 days, 20 hours ago
Selected Answer: A
In a structured cabling system, a central termination point is used to organize and manage network cables efficiently. This helps with maintenance, troubleshooting, and scalability. A patch panel is a centralized termination point where network cables from wall jacks are connected and managed.The MDF is the main network distribution point for the entire building, not just one floor.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago