exam questions

Exam PK0-005 All Questions

View all questions & answers for the PK0-005 exam

Exam PK0-005 topic 1 question 252 discussion

Actual exam question from CompTIA's PK0-005
Question #: 252
Topic #: 1
[All PK0-005 Questions]

During the planning phase, a team agreed on the tasks, durations, predecessors, and resources needed to complete a project. Which of the following should be developed to formalize this agreement?

  • A. Baseline
  • B. RBS
  • C. WBS
  • D. Milestones
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
ab00279
2 months ago
Selected Answer: C
A WBS visually represents the project tasks in a hierarchical structure, outlining how the project will be broken down into manageable components. It includes information like tasks, durations, predecessors, and resource allocation, which aligns with the scenario described in the question.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago