During the planning phase, a team agreed on the tasks, durations, predecessors, and resources needed to complete a project. Which of the following should be developed to formalize this agreement?
A WBS visually represents the project tasks in a hierarchical structure, outlining how the project will be broken down into manageable components. It includes information like tasks, durations, predecessors, and resource allocation, which aligns with the scenario described in the question.