Question #: 183
Topic #: 1
[All PK0-005 Questions]

A few weeks before a project is scheduled to be completed, the client asks to add a new feature to the product that is being developed. The project manager analyzes the project schedule and determines the feature can be implemented quite easily without affecting the completion date. Which of the following should the project manager do FIRST?

  • A. Escalate the change to the CCB.
  • B. Review the requested change.
  • C. Document the change recommendations.
  • D. Validate the implementation of the requested change.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
044f354
2 months ago
Selected Answer: B
The question is worded slightly tricky to misdirect a lazy reader. It may appear the PM has already 'reviewed' the change, but the PM has only consulted the calendar. The NEXT step is to analyze the request for aspects like feasibility, impact, and alignment with project goals.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago