A team is analyzing the backlog in order to decide what to include in the next sprint. Which of the following aspects is the MOST important for the team to take into consideration?
CompTIA Project+ Study Guide, 3rd Edition
Chapter 4: Planning the Project
"The user stories are prioritized so that the most important are at the top of the backlog list and those with less importance fall beneath these on the list."
The team should prioritize backlog items based on their significance to the project’s success.
Therefore B is the correct choice.
upvoted 1 times
...
This section is not available anymore. Please use the main Exam Page.PK0-005 Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
044f354
2 months ago