Exam PK0-005 topic 1 question 155 discussion

Actual exam question from CompTIA's PK0-005
Question #: 155
Topic #: 1
[All PK0-005 Questions]

A team is analyzing the backlog in order to decide what to include in the next sprint. Which of the following aspects is the MOST important for the team to take into consideration?

  • A. Time to be fixed
  • B. Impact to project
  • C. Issue category
  • D. Resource availability
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
044f354
2 months ago
Selected Answer: B
CompTIA Project+ Study Guide, 3rd Edition Chapter 4: Planning the Project "The user stories are prioritized so that the most important are at the top of the backlog list and those with less importance fall beneath these on the list." The team should prioritize backlog items based on their significance to the project’s success. Therefore B is the correct choice.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago