Prior to implementing a design change, the change must go through multiple steps to ensure that it does not cause any security issues. Which of the following is most likely to be one of those steps?

  • A. Board review
  • B. Service restart
  • C. Backout planning
  • D. Maintenance
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
test_arrow
2 months, 1 week ago
Selected Answer: C
Part of the change control process C. Backout planning Explanation: Before implementing a design change, organizations need a backout plan to ensure that if something goes wrong—such as security vulnerabilities, performance issues, or unexpected failures—they can quickly revert to the previous stable state. This minimizes downtime and potential security risks.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago