As a result of an approved change, the project manager updates the project plan with the newest project end date. Which of the following change control processes should the project manager complete next?

  • A. Document the request in the change control log.
  • B. Perform a Monte Carlo simulation.
  • C. Conduct an impact assessment.
  • D. Implement the change.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
GDLY
17 hours, 11 minutes ago
Selected Answer: D
After updating project plan, next step is implement
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel