exam questions

Exam PK0-005 All Questions

View all questions & answers for the PK0-005 exam

Exam PK0-005 topic 1 question 284 discussion

Actual exam question from CompTIA's PK0-005
Question #: 284
Topic #: 1
[All PK0-005 Questions]

As a result of an approved change, the project manager updates the project plan with the newest project end date. Which of the following change control processes should the project manager complete next?

  • A. Document the request in the change control log.
  • B. Perform a Monte Carlo simulation.
  • C. Conduct an impact assessment.
  • D. Implement the change.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
stinkle
2 weeks ago
Selected Answer: D
After updating the project plan, the next step in CCP is implementation
upvoted 1 times
...
bigjudy2560
2 months, 2 weeks ago
Selected Answer: D
Its D, per the documentation.
upvoted 2 times
...
1324c82
2 months, 4 weeks ago
Selected Answer: A
Documentation happens before implementation.
upvoted 1 times
bigjudy2560
2 months, 2 weeks ago
wrong, review the change control process.
upvoted 2 times
...
...
GDLY
3 months, 1 week ago
Selected Answer: D
After updating project plan, next step is implement
upvoted 2 times
1324c82
2 months, 4 weeks ago
Implementation comes after the change has been approved and documented.
upvoted 1 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago