Following the approval of a change by the CCB, which of the following should a project manager consider NEXT when deploying a new networking device into an existing production environment?

  • A. Maintenance window
  • B. Risk assessment
  • C. Operational security
  • D. Validation check
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Jorgee214
2 weeks, 4 days ago
Selected Answer: A
Answer is A: Maintenance Window, would be scheduled to ensure minimal downtime to implement the change since it does not state time is critical for this change to occur. Both a Risk Assessment and Operational Security Assessment would have been conducted prior to going to the CCB for consideration. While a Validation check is done after the change is implemented to ensure its function.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago