exam questions

Exam PK0-004 All Questions

View all questions & answers for the PK0-004 exam

Exam PK0-004 topic 1 question 155 discussion

Actual exam question from CompTIA's PK0-004
Question #: 155
Topic #: 1
[All PK0-004 Questions]

The project schedule performance index is 1.1, and the cost performance index is 0.9. Which of the following describes the project status?

  • A. Ahead of schedule and over budget
  • B. Behind schedule and under budget
  • C. Ahead of schedule and under budget
  • D. Behind schedule and over budget
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Steele08
Highly Voted 5 years, 2 months ago
The correct answer is A. Anytime the SPI or CPI are below 1.0, it has a negative affect on the project. It's ahead of schedule and over budget.
upvoted 22 times
brown705
2 years, 9 months ago
Absolutely incorrect. If CPI is < 1, you are spending less than anticipated.
upvoted 1 times
...
...
Havok
Highly Voted 5 years ago
Correct answer is we are ahead of schedule since index is >1.0, and over budget since index is <1.0.
upvoted 6 times
...
Alam8330
Most Recent 2 years ago
The cost performance index (CPI) measures the value of the work completed at the measurement date against the actual cost. It is one of the most important EVM measurements because it tells you the cost efficiency for the work completed to date or at the completion of the project. If CPI is greater than 1, you are spending less than anticipated at the measurement date. If CPI is less than 1, you are spending more than anticipated for the work completed at the measurement date. The cost performance index (CPI) is calculated this way: CPI = EV / AC Plug in the numbers to see where you stand: 70,000 / 71,000 = .99 Since the result is less than 1, it means cost performance is worse than expected.
upvoted 1 times
...
CyberRooster
2 years, 1 month ago
The project schedule performance index (SPI) is 1.1, which means the project is ahead of schedule, and the cost performance index (CPI) is 0.9, which means the project is under budget. Therefore, the project status can be described as "Ahead of schedule and under budget." The correct option is C.
upvoted 1 times
...
Noralie
2 years, 2 months ago
"The schedule performance index (SPI) measures the progress to date against the progress that was planned. This formula should be used in conjunction with an analysis of the critical path activities to determine whether the project will finish ahead of or behind schedule.*** If SPI is greater than 1, your performance is better than expected, and you’re ahead of schedule. If SPI is less than 1, you’re behind schedule at the measurement date."*** The cost performance index (CPI) measures the value of the work completed at the measurement date against the actual cost. It is one of the most important EVM measurements because it tells you the cost efficiency for the work completed to date or at the completion of the project. ***If CPI is greater than 1, you are spending less than anticipated at the measurement date. If CPI is less than 1, you are spending more than anticipated for the work completed at the measurement date.***
upvoted 1 times
...
[Removed]
2 years, 5 months ago
Selected Answer: A
Answer is A
upvoted 1 times
...
MJVIS
2 years, 6 months ago
Selected Answer: A
an SPI above 1 equates to being ahead of schedule, whereas an SPI under 1 means you're behind schedule. And, if your SPI is equal to 1, your project is exactly on schedule. In summary: SPI > 1: The project is ahead of schedule; more work has been completed than expected. If the ratio has a value higher than 1 then it indicates the project is performing well against the budget. A CPI of 1 means that the project is performing on budget. A CPI of less than 1 means that the project is over budget.
upvoted 1 times
...
ItsMeAgain99
2 years, 6 months ago
Selected Answer: A
Ahead of schedule and over budget.
upvoted 1 times
...
Jad11
2 years, 10 months ago
Selected Answer: A
The correct answer is AAAAAAAAAAAA
upvoted 1 times
...
catastrophie
3 years ago
Selected Answer: A
As others have stated the answer is A. SPI < 1 = Behind schedule SPI =1 is on schedule SPI >1 is ahead of schedule CPI < 1is Over budget CPI =1 is on budget CPI >1 is under budget
upvoted 2 times
...
Rob0645
3 years ago
The answer is A unless they are trying to say a SPI grater than one can offset the lower CPI
upvoted 1 times
...
Born_Again
3 years, 1 month ago
Selected Answer: C
C. Ahead of schedule and under budget
upvoted 2 times
...
Jo1988
3 years, 1 month ago
The correct answer is A How do you read the schedule performance index SPI? Formula: SPI = EV / PV. If the ratio has a value higher than 1 this indicates the project is progressing well against the schedule. If the SPI is 1, then the project is progressing exactly as planned. If the SPI is less than 1 then the project is running behind schedule. How do you interpret CPI in project Management? Formula CPI = EV / AC. The project manager will have a value of less than 1 (project over budget), of 1 (project on budget), or greater than 1 (project under budget). CPI in project management measures the cost efficiency of a project.
upvoted 1 times
...
sTryogetOn
3 years, 3 months ago
Selected Answer: A
It's A. source: https://projectmanagementacademy.net/resources/blog/cost-performance-index-cpi-for-pmp-exam-prep/
upvoted 3 times
...
JohnWH
3 years, 8 months ago
To reiterate the same thing others have said..... For Indexes, BELOW 1.0 results are BAD. CPI less than 1.0 = over budget......BAD CPI more than 1.0 = under budget......GOOD SPI less than 1.0 = behind schedule......BAD SPI more than 1.0 = ahead of schedule.......GOOD CORRECT ANSWER: A
upvoted 4 times
...
izz123
3 years, 10 months ago
Steele08 is correct. "Anytime SPI or CPI are below 1.0, it has a negative affect on the project. It's ahead of schedule and over budget."
upvoted 1 times
...
AlvMicro
4 years, 1 month ago
I think given answer is correct. Since: An SPI value less than one indicates that less work has been completed than planned, and an SPI greater than one indicates that more work has been completed than planned. A CPI greater than one indicates that the project is over budget, and a CPI less than one indicates that the project is under budget. https://learning.oreilly.com/library/view/comptia-project-cert/9780134713250/ch03.xhtml
upvoted 1 times
l0609890
4 years ago
No, a cpi greater than 1 is under budget while a cpi less than 1 is over budget.
upvoted 1 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago