Exam PK0-005 topic 1 question 165 discussion

Actual exam question from CompTIA's PK0-005
Question #: 165
Topic #: 1
[All PK0-005 Questions]

A project is running over budget, and due to new legislation in the country, the company needs to release all its contractors on the project or hire them as full-time employees. Which of the following should the PM do NEXT to comply with the new legislation?

  • A. Use only full-time employees even if the project is delayed.
  • B. Hire all team members to avoid any delay in the project.
  • C. Close the contract and pay the contractors cash for the remainder of the project.
  • D. Look for an overseas vendor to finalize the project work.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Jorgee214
2 weeks, 4 days ago
Selected Answer: A
Another CompTIA question that gets you with its wording.. I chose A with this reasoning. "Project is over budget... Country's las requires release or hire on full-time" Answer B & D requires more budget which will goes against the already over budget. B being a possibility, however I am thinking if you contract out work its temporary and cheaper in the short run (long run includes payroll, medical, etc..) C: implies paying the contractors "under the table" to complete the project which will never be an option. A is the only option in my opinion that complies with legislation, and the already over budget constraint. Note: it does not state whether the CCB will approve more funding to hire more individuals nor allow it to extend the timeline so just based off the information provided in the question A was the only conclusion I was able to come up with.
upvoted 1 times
...
gorilla2001
2 months, 3 weeks ago
Selected Answer: C
This option ensures compliance with the new legislation while also honoring the existing contracts with the contractors. Paying out the remainder of the contract allows the project to proceed in a legal and ethical manner, avoiding any complications that could arise from non-compliance.
upvoted 1 times
...
MACC357
5 months, 3 weeks ago
Selected Answer: B
In order to avoind delays and obey the laws it would be in the best interest of the PM to hire all team member and keep the project party going without delay.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago