A project team is defining operational training, discussing a go-live date, and describing the operational handoff. Which of the following BEST describes what the team is developing?
Per AI source...
D. A transition plan.
A transition plan outlines the activities and processes required to transition the project deliverables from the project team to the operational or support team. It typically includes details about training, go-live dates, operational handoff procedures, and any other activities necessary to ensure a smooth transition from project implementation to operational use. Developing a transition plan is essential for ensuring that the project's outcomes are effectively integrated into ongoing operations and support activities.
upvoted 2 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
eXhilarat3d
20 hours, 28 minutes ago