Question #: 182
Topic #: 1
[All PK0-005 Questions]

A project manager is eager to define access requirements during the initiation phase of a project. Which of the following steps should the project manager perform FIRST?

  • A. Define the WBS.
  • B. Develop a RAM.
  • C. Manage the vendors.
  • D. Assess the resource pool.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
joe99999
1 month ago
Selected Answer: B
B since Create Stakeholder Registry isn't an option. Everything else is in the Planning Phase.
upvoted 1 times
...
study_study
2 months, 1 week ago
Selected Answer: B
Per another? AI source... B. Develop a RAM (Responsibility Assignment Matrix) A Responsibility Assignment Matrix (RAM) helps clarify the roles and responsibilities of team members and stakeholders for project tasks, including defining who has access to what resources. By developing a RAM, the project manager can establish clear access control and resource responsibilities early on, which is crucial for effective project management and security.
upvoted 1 times
...
Illini
2 months, 2 weeks ago
Selected Answer: D
Per a different? AI source.... In the initiation phase of a project, before delving into detailed planning, the project manager should first understand the project scope and the overall resource needs. Therefore, the best first step would be: D. Assess the resource pool. This step allows the project manager to identify available resources, including skills and capacities, which is essential for defining access requirements and planning effectively for the project.
upvoted 1 times
...
eXhilarat3d
7 months, 1 week ago
Selected Answer: B
Per AI source... Develop a RAM (Responsibility Assignment Matrix). Developing a RAM, such as a RACI chart, helps to clarify the roles and responsibilities of team members in relation to project tasks and deliverables. This is particularly important when defining access requirements because it establishes who needs access to what information or areas of the project based on their responsibilities.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago