During an agile project, a team member checked the project artifacts in order to anticipate when all the work should have been completed. Which of the following charts was the team member MOST likely consulting?

  • A. Pareto chart
  • B. Milestone chart
  • C. Burndown chart
  • D. Gantt chart
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
eXhilarat3d
1 month, 1 week ago
Selected Answer: C
Burndown chart: This is a staple of Agile methodologies. It visually tracks the remaining work in a sprint by plotting the amount of work left (user stories, tasks, etc.) against time. By looking at the trend of the burndown chart, a team member can get a sense of when the remaining work is likely to be completed.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago