During a complex, multiyear project, a PM must discern which project tasks overlap so resources can be allocated appropriately. Which of the following is BEST for determining this information?
Gantt charts are a useful tool for project managers to visualize project tasks, dependencies, and timelines, which can help determine which tasks overlap.
A. PERT chart
PERT (Program Evaluation and Review Technique) charts are specifically designed to analyze task dependencies, durations, and the critical path in a project. They provide a visual representation of the project's timeline and help identify which tasks can overlap and which ones are dependent on each other. By using a PERT chart, project managers can allocate resources more effectively, ensuring that tasks are completed efficiently and on time. While Gantt charts, milestone charts, and budget burndown charts are also valuable project management tools, they may not offer the same level of detail and insight into task overlaps as PERT charts do.
upvoted 1 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
eXhilarat3d
1 month, 1 week agoTherealjosh
1 month, 3 weeks agoTherealjosh
1 month, 3 weeks ago