exam questions

Exam PK0-004 All Questions

View all questions & answers for the PK0-004 exam

Exam PK0-004 topic 1 question 102 discussion

Actual exam question from CompTIA's PK0-004
Question #: 102
Topic #: 1
[All PK0-004 Questions]

A project has activities on the critical path that must be completed before other activities can start.
Task A is dependent on Task C before Task D can be completed.
Task A requires task B to start.
Task B takes twice as long to complete as Task C.
Which of the following is the appropriate ordering of the critical path?

  • A. B, A, D
  • B. C, B, D, A
  • C. D, A, C
  • D. B, C, A, D
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Lesediii
2 years ago
Michael Jackson B.A.D
upvoted 1 times
...
Braniac
2 years, 7 months ago
So, B. C, B,D,A is the correct answer. A requires B to start and finish per the initial statement, not description. And is also dependent on C. B is also dependent on C. Task B is 1 of Task A's predecessors. But B needs a predecessor as well. B or C could be possible but for D to fit in correctly, B is dependent on C. So now, C,B. D only requires the dependcy of Task A to C to no longer be applicable. Once that dependency is gone, D can start, but must wait for B to finish. C,B,D,A. but it seems D could work as well.
upvoted 1 times
...
chernukha101
3 years, 6 months ago
This isn't funny at all. Waste of time. It reads 2B-A-D when you write down the diagram. (too bad, you wasted your time). There is no correct answer and this is not a genuine question. Ignore it.
upvoted 2 times
some_specialist
2 years, 10 months ago
lmao 2BAD 4u2 waste your time, I guess there are some troll questions in here
upvoted 3 times
...
...
dyers
3 years, 8 months ago
"Task A is dependent on Task C before Task D can be completed." how do you decipher this line? Besides the entire question is indeterminable because critical path is the longest path of tasks, but if A is 6 months and B,C,D are 1 month, all these "clues" don't matter at all. Without numbers, I don't see how the critical path can be determined at all.
upvoted 3 times
...
jerry47
5 years, 2 months ago
B,A,D seems better.
upvoted 3 times
Nygma
4 years, 9 months ago
How are you going to do A when it's dependent on C?
upvoted 5 times
...
brown705
2 years, 9 months ago
This question is B A D.
upvoted 2 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago