A local bank has all of its infrastructure in the cloud. An update was applied to the main database server at 5:00 a.m. on Monday morning, and the database was then corrupted and unusable. It had to be restored from backup. The last backup was taken the night before at 10:00 p.m. The database was then restored successfully, but seven hours' worth of data was lost, which is deemed unacceptable. Which of the following needs to be updated in the DR plan?
BlueMan93
20 hours, 49 minutes agoCXSSP
1 week, 4 days agonmap_king_22
8 months, 3 weeks ago