A project manager is performing planning tasks for a complex project at a small company. Which of the following items would be of GREATEST importance during planning?

  • A. Defining the project objectives, scope, and success criteria
  • B. Assessing the resources available for operational support after project implementation
  • C. Providing updates and status reports to the project owner and stakeholders
  • D. Developing a records management plan and reviewing existing project artifacts
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
bigjudy2560
2 months, 3 weeks ago
Selected Answer: B
It isnt A. A would occur during initiation, not planning. its probably B.
upvoted 1 times
...
DandyAndy
7 months, 1 week ago
Selected Answer: A
If you made it this far, good luck. I am hoping for the best for you.
upvoted 4 times
...
2f0b60f
1 year, 1 month ago
Selected Answer: A
The answer is A. Defining the project objectives, scope, and success criteria. Defining the project objectives, scope, and success criteria is the most important task during project planning. This is because it sets the foundation for the rest of the planning process. The project objectives should be specific, measurable, achievable, relevant, and time-bound. The scope should define the boundaries of the project and what is included and excluded. The success criteria should define how the project will be measured to determine if it was successful.
upvoted 1 times
...
jksdbfb
1 year, 1 month ago
Selected Answer: A
A is correct
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.