exam questions

Exam PK0-005 All Questions

View all questions & answers for the PK0-005 exam

Exam PK0-005 topic 1 question 133 discussion

Actual exam question from CompTIA's PK0-005
Question #: 133
Topic #: 1
[All PK0-005 Questions]

A project sponsor is notified that the committed turnaround time has been exceeded. The team member assigned to this item stated that the support of the management team was requested on time. Which of the following documents should be reviewed to understand the root cause of this situation?

  • A. RACI
  • B. SOW
  • C. Escalation path
  • D. Communication plan
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
joe99999
1 day, 23 hours ago
Selected Answer: D
Key is "the document". Escalation path is a part of the communications plan/document.
upvoted 1 times
...
2f0b60f
3 months ago
Selected Answer: C
The correct answer is C. Escalation path. The escalation path is a document that outlines the steps that should be taken when a problem arises in a project. It specifies who should be notified and when, and it also defines the actions that should be taken at each stage. In this case, the team member has stated that they requested the support of the management team on time. However, the support was not provided, which has caused the turnaround time to be exceeded. The escalation path will help to identify who should have been notified of the problem and when, and it will also help to determine what actions should have been taken.
upvoted 1 times
...
sheilawu
4 months ago
Selected Answer: C
If think straitly, I will go for C. For me, I will read the past threads and see the escalate path. wrong escalate path=>unsync the result.
upvoted 1 times
...
Dar87
4 months, 1 week ago
Selected Answer: D
This is hard to answer because the escalation path is a part of the communication plan and is used to escalate issues between stakeholders, pm, team members and resources.
upvoted 2 times
...
TheGinjaNinja
6 months, 2 weeks ago
Selected Answer: D
I'm not sure C or D - The Communication Plan outlines the communication protocols, channels, and stakeholders involved in the project. It specifies the frequency, methods, and escalation paths for communicating project updates, issues, and requests for support. By reviewing the Communication Plan, the project sponsor can gain insights into whether the management team was appropriately informed and engaged in a timely manner. It can help determine if there were any breakdowns in communication, whether the escalation path was followed correctly, and if the necessary support from the management team was indeed requested on time.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago