As a result of an approved change request, the project manager updates the project plan to reflect the new feature addition and the revised production release date. Which of the following change control processes should the project manager do NEXT?

  • A. Validate the change implementation.
  • B. Implement the change.
  • C. Conduct an impact assessment.
  • D. Communicate the change deployment.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Realiable_0
Highly Voted 11 months, 2 weeks ago
its actually B, Follow the change control Process. He already updated the plan next is to implement, then validate then communicate the change.
upvoted 12 times
...
Toobz1
Highly Voted 12 months ago
The stages of the change control process in CompTIA Project+ are: B. Implement the change. 1. Identify and document the change. 2. Evaluate the impact and justification of the change. 3. Identify the approval authority and obtain approval. 4. Implement the change. Once the change has been approved, the project manager needs to develop a plan for implementing it. This may involve making changes to the project plan, schedule, budget, or resources. 5. Validate the change and check the project quality. 6. Update relevant documents and communicate the change. 7. Develop a regression plan.
upvoted 8 times
...
stinkle
Most Recent 2 weeks, 1 day ago
Selected Answer: B
Doc Chng req log Prelim review impact analysis Doc chng recommendations Determine decision makers Escalate to CCB Doc status of decision in change log Update Project plan <<<<< You are here Implement change <<<< Next step Validate and Quality check Comm to stakeholders
upvoted 1 times
...
bigjudy2560
2 months, 3 weeks ago
Selected Answer: B
its B, per the documentation
upvoted 1 times
...
HappyG
5 months, 1 week ago
Selected Answer: B
After the project plan is updated, you implement the change according to objective 1.3, change control process.
upvoted 2 times
...
[Removed]
6 months, 2 weeks ago
Selected Answer: A
A -because validating comes after updating the project plan
upvoted 1 times
...
2f0b60f
1 year, 1 month ago
Selected Answer: C
The answer is C. Conduct an impact assessment. After the project manager updates the project plan, the next step is to conduct an impact assessment. This will help to identify the impact of the change on the project, such as the impact on the budget, schedule, and scope. The impact assessment will also help to identify any risks associated with the change. Once the impact assessment is complete, the project manager can then implement the change. This includes making the necessary changes to the project schedule, budget, and scope. The project manager should also communicate the change to the project team and stakeholders.
upvoted 1 times
Granddude
1 year, 1 month ago
I think the impact assessment should be performed before the change was submitted for approval.
upvoted 2 times
...
...
jksdbfb
1 year, 1 month ago
Selected Answer: D
D - Communicating the change deployment is the next step in the change control process. It's important to inform all relevant stakeholders about the approved change, the updates made to the project plan, and any adjustments to timelines or other project elements. This ensures that everyone is aware of the changes and can align their actions and expectations accordingly. Once the change has been effectively communicated, the project manager can move forward with implementing the change and validating its implementation.
upvoted 2 times
...
Dar87
1 year, 2 months ago
Selected Answer: D
It’s already been approved.
upvoted 1 times
Dar87
1 year, 2 months ago
If the change request is approved then the project deliverables will need to be updated. This can include plans and schedules, business process documents, and the requirements documents. Once these updates have been made, the project manager can communicate the new course of action to everyone who will be impacted. -Talley.com
upvoted 1 times
...
...
TheGinjaNinja
1 year, 4 months ago
Selected Answer: C
Conducting an impact assessment is the next logical step in the change control process.
upvoted 1 times
Noahtmt1510
1 year, 3 months ago
Impact assessment comes before approval. Change has been approved, you would communicate the change then implement the change.
upvoted 2 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago