exam questions

Exam 220-1101 All Questions

View all questions & answers for the 220-1101 exam

Exam 220-1101 topic 1 question 198 discussion

Actual exam question from CompTIA's 220-1101
Question #: 198
Topic #: 1
[All 220-1101 Questions]

A technician recently received a written warning for causing a system-wide outage. The outage was a result of an unscheduled patch being manually pushed during production hours. Which of the following could have MOST likely prevented the technician from receiving the warning?

  • A. Following corporate procedures
  • B. Testing before deployment
  • C. Documenting the findings
  • D. Establishing a plan of action
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
JonHin
2 months ago
A is the best answer Following corporate procedures would have been the most likely factor that could have prevented the technician from receiving the written warning. Following established procedures, such as change management, helps ensure that changes made to the production environment are thoroughly tested, approved, and implemented in a controlled and safe manner, reducing the risk of system-wide outages and other unintended consequences.
upvoted 1 times
...
ZenBurrito
10 months, 1 week ago
Selected Answer: A
"written warning for causing a system-wide outage. The outage was a result of an unscheduled patch being manually pushed during production hours" directly indicates that the technician did NOT know the procedure. Even if the technician tested before pushing the update through manually, he still would have made the error of doing it during production hours so it cannot be B. Testing is important, but in this scenario would still result in a mistake being made
upvoted 4 times
...
BestSumy
11 months, 2 weeks ago
Selected Answer: B
Agree with Com since you definitely need to test every patch/update/driver whatsoever before push to company wide, it is ok to have one single affected testing machine
upvoted 1 times
...
PatrickH
11 months, 3 weeks ago
Its A. YOu MUST follow procedures (if they exist). Pusing through a patch during production hours is a massive NoNo. YOu just dont do that unless its a desperate Malware attack situation for example. Follow the Proceedures which would almost certainly involve Testing BUT testing is only a part of it
upvoted 3 times
...
ComPCertOn
1 year, 2 months ago
Selected Answer: B
I think B makes more sense since the technician should have tested the patch before releasing it. while A is a valid choice too nothing indicates the technician didn't follow the policy procedure.
upvoted 4 times
Russell15
9 months, 3 weeks ago
Homie, there was nothing wrong with the patch it worked as expected. Pushing said patch during business hours stopped everyone from working on the system that was being updated. A for sure.
upvoted 2 times
...
...
AustinKelleyNet
1 year, 5 months ago
Selected Answer: A
This should be A. If they would have tested, they would have seen the outage happen in a nonproduction environment.
upvoted 4 times
SR1991
1 year ago
Then you mean B
upvoted 2 times
SugarCoatedLies
10 months, 2 weeks ago
No, you always follow policy, he'd get hemmed up for not following policy otherwise.
upvoted 2 times
...
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago