A new project has started, and the project schedule is being built. After the WBS is complete, scheduling of the activities begins. Which of the following is the most likely NEXT step?

  • A. Sequence the activities.
  • B. Allocate the resources.
  • C. Set the baseline.
  • D. Determine the tasks.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
NextTopic
1 year, 11 months ago
Selected Answer: D
Determine the tasks.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.