exam questions

Exam PK0-004 All Questions

View all questions & answers for the PK0-004 exam

Exam PK0-004 topic 1 question 840 discussion

Actual exam question from CompTIA's PK0-004
Question #: 840
Topic #: 1
[All PK0-004 Questions]

Which of the following is the BEST time to establish the project cost baseline?

  • A. After the WBS is created
  • B. During sprint planning
  • C. Before the project charter is signed
  • D. During the project kickoff meeting
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️
It is a best practice to set the baseline of the schedule Before the project charter is signed.

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
NextTopic
1 year, 11 months ago
To me A seems like the more logical answer but it can't be C
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel