A key stakeholder reviews the project charter and expresses concern that the milestones are not documented. Which of the following should the project manager do?
A.
Direct the key stakeholder to review the project management plan
B.
Add the baselines to the charter after a change request has been approved
C.
Document the key stakeholder’s concerns in the issue log
D.
Provide the key stakeholder with a status report to show where the project currently stands
B does not make any sense. A would be the answer. Why would the baseline be apart of the project charter?
upvoted 1 times
...
This section is not available anymore. Please use the main Exam Page.PK0-004 Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
NextTopic