A key stakeholder reviews the project charter and expresses concern that the milestones are not documented. Which of the following should the project manager do?

  • A. Direct the key stakeholder to review the project management plan
  • B. Add the baselines to the charter after a change request has been approved
  • C. Document the key stakeholder’s concerns in the issue log
  • D. Provide the key stakeholder with a status report to show where the project currently stands
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
NextTopic
1 year, 11 months ago
B does not make any sense. A would be the answer. Why would the baseline be apart of the project charter?
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago