Exam PK0-005 topic 1 question 36 discussion

Actual exam question from CompTIA's PK0-005
Question #: 36
Topic #: 1
[All PK0-005 Questions]

Due to multiple changes, the sign-off for the project scope baseline is delayed. The project sponsor has restricted the budget for this project. Which of the following should the project manager MOST likely do to move forward?

  • A. Communicate with the affected stakeholders.
  • B. Initiate a formal change request to modify the cost.
  • C. Adjust the scope to stay within the cost.
  • D. Set a new cost using a lightweight estimation method.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
TheGinjaNinja
Highly Voted 1 year, 11 months ago
Selected Answer: A
The project manager should communicate with the affected stakeholders first after realizing that the sign-off for the project scope baseline is delayed due to multiple changes and that the budget for this project is restricted by the project sponsor. The affected stakeholders are those who have an interest or influence on the project and may be impacted by any changes or delays. Communicating with them can help to explain the situation, assess the impact, seek feedback, and manage expectations.
upvoted 6 times
MACC357
9 months, 1 week ago
How does this address the issue that the project sponsor has restricted the budget for this project. Communicating to the stakeholder is important but in order to keep the project moving the budget needs to be addressed and since it is restricted some adjustments need to be made to keep the ball rolling on
upvoted 1 times
...
...
95d3b92
Most Recent 2 months ago
Selected Answer: C
It makes most sense to adjust the scope first, then communicate it to the affected stakeholders since the sponsor has restricted the budget.
upvoted 1 times
...
AdmiralGimme
1 year ago
Maybe I am wrong, but I feel like it should be B. Initiate a formal change request? I think this would be the first thing most likely after which A and C would both occur.
upvoted 3 times
...
TheFai
1 year, 1 month ago
Selected Answer: A
Stakeholders need to know. Its already delayed anyways so submitting a change first doesn't make much sense when more changes will be coming once the Stakeholders know.
upvoted 1 times
...
Narobi
1 year, 5 months ago
Selected Answer: C
Communicating with stakeholders will not move the project forward. You need to get through the issue stopping the project which is the budget. C would address this issue.
upvoted 1 times
...
2f0b60f
1 year, 7 months ago
Selected Answer: A
Communicate with the affected stakeholders: This is the most prudent initial action to ensure everyone understands the implications of the delayed sign-off and the restricted budget. It's essential to align expectations and come to a mutual agreement on how to proceed.
upvoted 1 times
...
JohnLarsen
1 year, 7 months ago
Selected Answer: C
Among these options, "Customer Notification" (Option C) would be the most appropriate item to add to the issue log in this specific context. The issue seems to center around stakeholders not being adequately informed about the extended downtime, and therefore a lack of or insufficient customer notification would be the closest match for the problem that needs to be resolved.
upvoted 1 times
...
jksdbfb
1 year, 7 months ago
Selected Answer: A
the MOST LIKELY answer is A
upvoted 2 times
...
Dar87
1 year, 8 months ago
Selected Answer: A
Talk with affected skaeholders because they may not get everything they requested.
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago