A number of requirements, conflicts, and reworks during a project delayed the schedule, increased the budget, and required replanning efforts. Which of the following is MOST likely the cause?
A.
There were not enough resources assigned to the project execution team.
B.
The PMO was not involved in project initiation and planning.
C.
Proper team-building activities were not performed when starting the project.
D.
A few major stakeholders were overlooked during project initiation and planning.
I think it's D. Idk why the PMO would be involved other than supplying template or necessary documents. Having major stakeholders overlooked during the initiation of your project is bad.
upvoted 1 times
...
This section is not available anymore. Please use the main Exam Page.PK0-004 Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.