exam questions

Exam PK0-004 All Questions

View all questions & answers for the PK0-004 exam

Exam PK0-004 topic 1 question 494 discussion

Actual exam question from CompTIA's PK0-004
Question #: 494
Topic #: 1
[All PK0-004 Questions]

A number of requirements, conflicts, and reworks during a project delayed the schedule, increased the budget, and required replanning efforts.
Which of the following is MOST likely the cause?

  • A. There were not enough resources assigned to the project execution team.
  • B. The PMO was not involved in project initiation and planning.
  • C. Proper team-building activities were not performed when starting the project.
  • D. A few major stakeholders were overlooked during project initiation and planning.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
NextTopic
1 year, 12 months ago
Selected Answer: D
I think it's D. Idk why the PMO would be involved other than supplying template or necessary documents. Having major stakeholders overlooked during the initiation of your project is bad.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago