exam questions

Exam PK0-005 All Questions

View all questions & answers for the PK0-005 exam

Exam PK0-005 topic 1 question 80 discussion

Actual exam question from CompTIA's PK0-005
Question #: 80
Topic #: 1
[All PK0-005 Questions]

A system was implemented, and testing was successfully completed. Which of the following should the project manager do NEXT?

  • A. Validate against the scope statement and ask for sign-off.
  • B. Run a control chart to ensure the quality of the deliverables.
  • C. Review the risk register and close up residual risks.
  • D. Start the training and handoff for the operations team.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
stinkle
2 weeks, 1 day ago
Selected Answer: A
Closing Phase Complete Testing: Verify that deliverables meet requirements. Validate Deliverables: Check that scope has been met and obtain sign-off. Close Risk Register: Address residual risks. Release Resources: Free up team members and equipment. Conduct Lessons Learned: Document what worked and areas for improvement. Handover Deliverables: Transition completed product to operations. Archive Documents: Store project documents for future reference. Formal Project Closeout: Officially close the project and confirm success.
upvoted 1 times
...
gorilla2001
6 months, 1 week ago
Selected Answer: A
D starts after A is completed
upvoted 1 times
...
Therealjosh
11 months, 2 weeks ago
Selected Answer: A
The project manager should validate against the scope statement and ask for sign-off after a system was implemented and testing was successfully completed. The scope statement is a document that defines and documents the project scope, objectives, deliverables, requirements, assumptions, and constraints. The scope statement can help to establish a common understanding and agreement between the project manager and the stakeholders on what the project aims to achieve and deliver. Validating against the scope statement means checking whether the project deliverables meet the agreed-upon scope criteria and quality standards. Asking for sign-off means requesting formal acceptance and approval of the project deliverables from the stakeholders.
upvoted 2 times
...
2f0b60f
1 year, 7 months ago
Selected Answer: A
Once a system has been implemented and testing successfully completed, the next logical step for the project manager would be "A. Validate against the scope statement and ask for sign-off."
upvoted 1 times
...
jksdbfb
1 year, 7 months ago
Selected Answer: A
The reason is that after testing is completed, the project manager should verify that the project deliverables meet the requirements and expectations of the stakeholders, as defined in the scope statement. The project manager should also obtain formal acceptance and approval from the stakeholders, which is known as sign-off.
upvoted 1 times
...
lamborghini
1 year, 11 months ago
Selected Answer: D
After the system has been implemented and testing has been successfully completed, the next step is to train the operations team on how to use the system. This will ensure that the system is used effectively and efficiently. The project manager should also hand off the system to the operations team so that they can take ownership of the system and support its ongoing use. The other options are not as important at this stage. The scope statement has already been validated, and the quality of the deliverables has already been ensured through testing. The risk register can be reviewed and residual risks can be closed up later, after the system has been in use for a while.
upvoted 4 times
jksdbfb
1 year, 7 months ago
Negative, you need to validate against the scope statement since although the statement had been signed before any work started you still need to make sure that everything in the scope statement is in the finished product .
upvoted 1 times
...
lamborghini
1 year, 11 months ago
(Bard) The risk register should be reviewed and residual risks should be closed up, but this is not the next step after the system has been implemented and testing has been successfully completed. The next step is to train the operations team on how to use the system and hand off the system to them. Once the operations team has been trained and the system has been handed off, then the project manager can review the risk register and close up residual risks.
upvoted 3 times
Narobi
1 year, 5 months ago
You used Bard to respond to C. jksdbfb is saying A is the answer. Reliance on AI to give you holistic answers will not get you very far. The answer is A btw. You need to get sign off that the project delivered what was in the scope before you can hand it over. You can't give an unfinished project to operations so you need the validation that you met all the requirements before handing it off.
upvoted 2 times
...
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago