Question #: 23
Topic #: 1
[All PK0-005 Questions]

In a functional organization, a project has been completed successfully. Which of the following actions would the project manager MOST likely perform?

  • A. Assemble a new project with existing resources.
  • B. Obtain the final report from release management.
  • C. Notify the functional manager that resources are released.
  • D. Allocate resources in a different project.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Caoilfhion
Highly Voted 1 year ago
Selected Answer: B
These AI answers in these discussion comments aren't taking a wholelistic approach and are leading one in the wrong direction. It is B because even though the project is completed, the PM needs a report before they request resource release, to make sure everything is in fact complete/resources no longer needed. Because once the resources are gone, they're gone. Then, the functional manager can be notified.
upvoted 6 times
wharftargo
1 year ago
my future is in your hands.. im trusting you on most these discussions lol
upvoted 2 times
Caoilfhion
11 months, 3 weeks ago
Good luck! The answers given here were on the exam and I passed with a near perfect score. You'll do great. :)
upvoted 6 times
...
...
...
lamborghini
Highly Voted 1 year, 6 months ago
Selected Answer: C
(Bard) The correct answer is C. Notify the functional manager that resources are released. In a functional organization, employees are assigned to projects on a temporary basis. When a project is completed, the employees are released back to their functional manager. The project manager is responsible for notifying the functional manager that the resources are available.
upvoted 6 times
...
044f354
Most Recent 2 months, 1 week ago
Selected Answer: C
ANSWER C: Releasing project resources happens before final project report is released PEOPLE!!! Stop relying on AI tools and people who don't use citations for these answers. From CompTIA Project+ Study Guide, 3rd Edition By Kim Heldman (ISBN 9781119892458) Chapter 10 - Managing Quality and Closing Out the Project Steps in Closing Out a Project Project closeout involves accepting the final product or service of the project and then turning it over to the organization. Closing out a project involves several steps: Verification and validation of deliverables Obtaining formal sign‐off Developing a transition plan and operational handoff Removing access **Releasing project resources** Closing out contracts Archiving documentation Conducting lessons learned and project evaluation Project closure meeting Project closeout report Rewards and celebration Postimplementation support and warranty period
upvoted 1 times
...
TheFai
7 months ago
Selected Answer: B
You would need to finalize everything and get the report to release your resources, before you could notify the functional manager that they are released. Think very bureaucratically.
upvoted 2 times
...
TheGinjaNinja
1 year, 5 months ago
Selected Answer: C
The project manager should notify the functional manager that resources are released after completing a project successfully in a functional organization. A functional organization is a type of organizational structure where employees are grouped by their functions or specialties, such as finance, marketing, or engineering. In a functional organization, the functional manager has more authority and control over the resources than the project manager. Therefore, the project manager should inform the functional manager when the resources are no longer needed for the project and can be reassigned to other tasks or projects.
upvoted 5 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago