While preparing to plan a project, the project manager meets with the key stakeholders to determine the flexibility between the project constraints. Which of the following techniques should the project manager consider to reduce personal bias and increase buy-in?

  • A. Send the stakeholders a survey about the project constraints to complete anonymously
  • B. Watch and determine which constraint is most important
  • C. Compare the constraints two at a time and have the stakeholders vote on importance
  • D. Look at historical information regarding the flexibility preferences of key stakeholders
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
NextTopic
2 years ago
...complete anonymously? I feel like C is the answer. While D sounds sensible if they are not around. To have them there you can discus what is currently needed.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.