Question #: 15
Topic #: 1
[All PK0-005 Questions]

During the stabilization phase for recently deployed software, an end user reports a bug that is compromising data integrity. Which of the following tools will the project manager MOST likely use?

  • A. Issue log
  • B. Defect log
  • C. Change log
  • D. Task board
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
BlueMan93
Highly Voted 1 year, 6 months ago
Selected Answer: B
A defect log is used in software development when defects (or bugs) are found during testing and after release. (pg 327 - "The Official CompTIA Project+ Guide (PK0-005)"
upvoted 5 times
...
044f354
Most Recent 2 months, 1 week ago
Selected Answer: A
ANSWER A: When you see “MOST likely use” in the context of PMBOK®: "Issue log" is the recognized, broad repository for ANYTHING requiring resolution. "Defect log" is not a PMBOK® artifact, even though it’s common in software development. "Change log" tracks the status of change requests once they’ve been formally submitted and accepted or rejected. "Task board" (or Kanban board) can be used in Agile or hybrid environments, but it’s more of a visual management tool for tasks and workflow—less about formally registering a problem that requires escalation or resolution in a PMBOK® sense. Hence, from the PMI/PMBOK® perspective, “Issue log” is the correct place to record any new bug or data‐integrity problem that arises.
upvoted 1 times
...
throughthefray
5 months, 2 weeks ago
Selected Answer: B
A would be for issues that arise in a project over all B is specifically for software projects, which the question states that it is.
upvoted 1 times
...
hardware69
6 months, 3 weeks ago
TheFai that is because there is no such log. We have trolls in this forum and it is very concerning, because we are actually trying to obtain information to pass and move on. Table 1.1 Project Management Documents. Change and Issue log...
upvoted 1 times
...
AdmiralGimme
6 months, 4 weeks ago
Selected Answer: B
Bug = Defect
upvoted 1 times
...
TheFai
7 months ago
Selected Answer: A
I cannot find the verbiage Defect Log anywhere in my Sybex book. Issue Log is mentioned repeatedly however, and is used for this exact case.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago