exam questions

Exam PK0-005 All Questions

View all questions & answers for the PK0-005 exam

Exam PK0-005 topic 1 question 11 discussion

Actual exam question from CompTIA's PK0-005
Question #: 11
Topic #: 1
[All PK0-005 Questions]

By developing a project schedule, a PM has already validated the constraints, outlined the duration of the tasks and the phases, and confirmed the proper sequence and flow of the project. Which of the following activities still needs to be performed to complete the schedule?

  • A. Allocate resources.
  • B. Determine the project budget.
  • C. Develop a communication plan.
  • D. Establish baselines.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
ExamNinja1
2 months, 3 weeks ago
Selected Answer: A
Developing a schedule in Project+: • Identify Tasks • Estimate Durations • Sequence Tasks • Resource Requirements • Allocate Resources • Create Schedule • Validate • Set Baselines • Document/Communicate • Monitor/Update
upvoted 1 times
...
AdmiralGimme
7 months ago
Selected Answer: D
Chat GPT says D. I think its reasoning is solid. During the scheduling phase, the project manager may review the planned schedule, adjust task durations, sequences, dependencies, and resource assignments as necessary to ensure feasibility and alignment with project objectives. Establishing baselines during the scheduling phase involves setting the schedule baseline, which includes freezing the schedule to reflect the agreed-upon plan against which actual progress will be measured. Therefore, even though establishing baselines is typically associated with the planning phase, it's also an essential activity during the scheduling phase to complete and formalize the project schedule before moving into execution and monitoring phases.
upvoted 1 times
...
TheFai
7 months ago
Selected Answer: A
You've already established baselines by outlining the duration. Now we just need to assign someone to the work.
upvoted 1 times
...
b0ad9e1
10 months, 2 weeks ago
Selected Answer: A
The answer is A, allocate resources. See Comptia Project+ section 1.6 Execute and Develop Project Schedules. Allocation of resources comes before setting baselines.
upvoted 4 times
...
Caoilfhion
1 year ago
Selected Answer: D
Answer: D (please disregard my other comment, selected wrong answer and it will not allow me to delete) Resources cannot be allocated until baselines are established. In other words, how would the PM know how much each section needs from a limited resource pool if it is unknown (even in estimate) how much is considered adequate?
upvoted 2 times
Narobi
12 months ago
This is done in the planning phase not the scheduling phase. Meaning it’s already been done by this point.
upvoted 1 times
Caoilfhion
11 months, 3 weeks ago
I passed this exam with a near perfect score using the answers from here. Unfortunetly, the answer to this question is still D based on the logic given above to explain the answer.
upvoted 4 times
...
...
...
Caoilfhion
1 year ago
Selected Answer: A
Resources cannot be allocated until baselines are established. In other words, how would the PM know how much each section needs from a limited resource pool if it is unknown (even in estimate) how much is considered adequate?
upvoted 1 times
...
jksdbfb
1 year, 1 month ago
Selected Answer: A
Although the project manager has validated constraints, outlined durations, and confirmed sequencing, the schedule is not complete until resources have been allocated. This involves assigning the necessary personnel, equipment, and materials to each task, ensuring that they are available when needed and that their use is optimized.
upvoted 1 times
...
BlueMan93
1 year, 6 months ago
Selected Answer: A
Agree, answer is A - you have to assign resources during the development of the project schedule.
upvoted 3 times
...
SkylarC
1 year, 6 months ago
Selected Answer: A
A. Allocate resources still needs to be performed to complete the project schedule. Developing a project schedule involves identifying the tasks, estimating their duration and sequencing them in the proper order. Once the tasks have been sequenced, the project manager needs to allocate resources to each task to ensure that the tasks are adequately staffed to complete them as outlined in the schedule. Resource allocation also ensures that the project is staffed with the right skills and that the resources are working on the right tasks at the correct levels of effort.
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago