A key stakeholder asks the project manager for additional features. Which of the following documents should the project manager refer to before responding to this request?
B. Change control plan.
The Change Control Plan outlines the process for handling requests for changes to the project scope, schedule, or budget. It specifies how changes will be evaluated, approved, implemented, and communicated. By referring to the Change Control Plan, the project manager can determine whether the requested additional features fall within the scope of the project and whether they are feasible and justifiable.
upvoted 1 times
...
This section is not available anymore. Please use the main Exam Page.PK0-004 Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
CyberRooster
2 years, 1 month ago