Question #: 217
Topic #: 1
[All PK0-004 Questions]

During the storming stage of a project team's development, it is common to experience confusion about tasks and responsibilities because:

  • A. there is unfamiliarity with the project structure.
  • B. there is a lack of trust among team members.
  • C. there are minimal team decisions.
  • D. there is no engagement of the team by the project manager.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️
Reference:
https://toggl.com/stages-of-team-development/

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
CyberRooster
2 years, 1 month ago
The correct answer is A. There is unfamiliarity with the project structure during the storming stage of a project team's development, leading to confusion about tasks and responsibilities. In this stage, team members are still getting to know each other and how they fit into the project, which can lead to disagreements and confusion about roles and responsibilities. It is important for the project manager to provide clear guidance and support during this stage to help the team work through these issues and move on to the norming stage.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago