Which of the following is the project phase when quality assurance occurs?

  • A. Planning
  • B. Closing
  • C. Execution
  • D. Scoping
  • E. Initiation
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️
Reference:
https://www.pm4dev.com/resources/free-e-books/5-project-quality-management/file.html
(9)

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
papahawaii
2 years, 1 month ago
Selected Answer: C
Quality assurance occurs during the implementation phase of the project and includes the evaluation of the overall performance of the project on a regular basis to provide confidence that the project will satisfy the quality standards defined by the project. Implementation = Execution
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago