A project is in the initiation phase. Which of the following tasks will take place during this phase?

  • A. Develop a WBS.
  • B. Define the project requirements.
  • C. Create a project charter.
  • D. Acquire the project resources.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
CyberRooster
2 years, 1 month ago
C. Create a project charter. The initiation phase is the first phase of the project management process, where the project's scope, objectives, and stakeholders are identified, and a project charter is created. The project charter defines the project's vision, objectives, scope, and high-level requirements and is approved by the project sponsor and stakeholders. The other tasks mentioned, such as developing a WBS, defining project requirements, and acquiring project resources, typically take place in the planning phase.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago