A responsibility assignment matrix (RAM) should include the following elements:
A. Responsible: the person or team responsible for completing the task or activity.
B. Accountable: the person who has ultimate responsibility for the completion of the task or activity.
C. Consulted: the person or team who is consulted for input or advice on the task or activity.
D. Informed: the person or team who is kept informed of the progress or status of the task or activity.
Therefore, the correct answer is A. Responsible, accountable, consulted, informed.
upvoted 1 times
...
This section is not available anymore. Please use the main Exam Page.PK0-004 Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
CyberRooster
2 years, 1 month ago