A project manager wants to introduce the practice of a WBS to the PMO, but the other managers believe this will create extra work. Which of the following would BEST communicate the need for a WBS to the other managers? (Choose two.)
A.
Using the WBS will help prevent work from slipping or being forgotten.
B.
TheWBS will be required on very large projects.
C.
TheWBS will be required if the project manager has the time available to complete it.
D.
TheWBS will aid in determining which resources are required for the project.
E.
The WBS is the best way to determine risks of the project.
A. Using the WBS will help prevent work from slipping or being forgotten.
D. The WBS will aid in determining which resources are required for the project.
Explanation: The WBS is an essential tool for breaking down a project into manageable work packages, which aids in preventing work from being overlooked or delayed. Additionally, by breaking down the project, the project manager can determine which resources are required for each package of work. These points are likely to resonate with the other managers, making the benefits of the WBS more apparent.
upvoted 1 times
...
This section is not available anymore. Please use the main Exam Page.PK0-004 Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
CyberRooster
2 years, 1 month ago