Question #: 123
Topic #: 1
[All PK0-004 Questions]

A team member learns that an assigned task is not due until the very end of the project. Moreover, the team member is not aware of any predecessor tasks dependent on completing the assigned task. Which of the following does the project manager use to decide if the team member can start the task later or earlier?

  • A. Review the PERT chart and evaluate if the task is a critical dependency.
  • B. Review the PERT chart and evaluate if the task is a discretionary dependency.
  • C. Review the PERT chart and evaluate if the task is a real dependency.
  • D. Review the PERT chart and evaluate if the task is an external dependency.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
CyberRooster
2 years, 1 month ago
A. Review the PERT chart and evaluate if the task is a critical dependency. By reviewing the PERT chart, the project manager can determine if the task is on the critical path, which means it is necessary to complete the project on time. If the task is not on the critical path, it may be possible to start it later or earlier without impacting the project schedule.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago