Which of the following Agile ceremonies is used to determine the backlog items that will be worked on the next weeks?

  • A. SCRUM retrospective meeting
  • B. Sprint planning meeting
  • C. Daily standup meeting
  • D. Review meeting
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️
Reference:
https://www.atlassian.com/agile/ceremonies

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
CyberRooster
2 years, 1 month ago
B. Sprint planning meeting The Agile ceremony used to determine the backlog items that will be worked on the next weeks is the Sprint planning meeting. The Sprint planning meeting is a collaborative meeting where the Product Owner and the Development Team decide which items from the product backlog they will work on during the upcoming Sprint
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago