exam questions

Exam PK0-004 All Questions

View all questions & answers for the PK0-004 exam

Exam PK0-004 topic 1 question 93 discussion

Actual exam question from CompTIA's PK0-004
Question #: 93
Topic #: 1
[All PK0-004 Questions]

An authorized change to a construction project was implemented. During the modification, the team identified a defect in which the change caused the building power output to be outside the KPPs.
Which of the following actions should the project manager take?

  • A. Submit a new change request.
  • B. Initiate the regression plan.
  • C. Add remediation to the schedule.
  • D. Accept the new power output.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 294

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
CyberRooster
2 years, 1 month ago
Tough one, but I think I'm gonna go with A. Submit a new change request. If a defect is identified in a construction project due to an implemented change, the project manager should submit a new change request. The change request should detail the defect and the necessary modifications required to rectify the situation, including the impact on the Key Performance Parameters (KPPs).
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago