Due to a new government regulation, a project change is required. The project manager evaluates the change and realizes a representative from the legal department will need to approve the change as well. The project manager should:
A.
follow the change process flow and notify the legal department after the change is implemented.
B.
extend a formal invitation to the legal department representative to join the CCB.
C.
hold a separate meeting with the legal department representative and ask for approval.
D.
notify the legal department representative in the event of an upcoming audit.
B. Extend a formal invitation to the legal department representative to join the CCB.
The change process should involve all stakeholders who may be impacted by the change. In this case, since the new government regulation requires approval from the legal department, the project manager should invite a representative from the legal department to join the Change Control Board (CCB) responsible for evaluating and approving changes to the project.
upvoted 2 times
...
This section is not available anymore. Please use the main Exam Page.PK0-004 Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
CyberRooster
2 years, 1 month ago