exam questions

Exam PK0-004 All Questions

View all questions & answers for the PK0-004 exam

Exam PK0-004 topic 1 question 757 discussion

Actual exam question from CompTIA's PK0-004
Question #: 757
Topic #: 1
[All PK0-004 Questions]

During the first several months of effort, a project manager reported all metrics at green status. However, during the most recent gate check, many metrics declined to red. Which of the following is the MOST likely reason the project manager was unable to predict the decline?

  • A. The SWOT analysis was not performed during planning.
  • B. The KPIs did not contain the required detail.
  • C. The RACI matrix was not followed.
  • D. The estimated task durations in the WBS were incorrect.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
MJVIS
2 years, 2 months ago
Selected Answer: D
This is what I found on the web, and the answer makes sense. The MOST likely reason the project manager was unable to predict the decline in the project metrics, despite reporting all metrics at green status for several months, is that the estimated task durations in the work breakdown structure (WBS) were incorrect. The WBS is a hierarchical decomposition of the project into smaller, more manageable components that can be planned, scheduled, and tracked. The estimated task durations in the WBS are an important input into the project schedule and help the project manager to track progress against the baseline plan. If the estimated task durations in the WBS are incorrect, the project manager may not have an accurate view of the project's progress, which can lead to a failure to predict a decline in metrics.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago